Heat Recovery System Tower Replacement
Owner: NDA
Location: U.S.
Contract Amount: $4,658,947
Completion: September 2020
Work focused on the renovation of the mine tunnel used for dewatering purposes. Project scope included but was not limited to installation of motor control, power distribution (120v to 12,470v), protection of existing cables, Leaky Feeder communication, maintenance OS existing equipment and aiding PKS with their electrical. Often required a crew 24 hrs., 7 days a week. Included 20,000+ feet of underground tunneling.