Silver Creek Water Reclamation Facility Expansion
Location: Park City, Utah
Contract Amount: $5,581,905
Project Amount: $45 Million
Completion: March 2020
Constructed a new 30 million gallon per day, activated-sludge treatment plant as an expansion to an existing facility.
Headworks facility, raw sludge pump station, two primary clarifiers, aeration basins, blower building, four secondary clarifiers with RAS/WAS pump station, de-chlorination building, two anaerobic digesters, digester control building, and a sludge thickening building. Skyline completed all phases of electrical work, including: designed and installed a large 5kilovolt temporary power grid in the first phases of the project; put in all major site duct banks; a new medium voltage system throughout plant which included multiple unit substation locations and transfer switches for a new onsite 2 megawatt backup generator which were mostly parallel medium voltage terminations; installed numerous pumps ranging from 1.5 up to 300 horsepower, including all programmable logic controls and local control panels; all applicable wiring for new facilities; and wiring in a new security and fire alarm system throughout all new buildings in the plant.